Calibration of the existing Food testing laboratory equipment & training of laboratory technicians (4technicians)
$3000-5000 USD
Κλειστή
Αναρτήθηκε περίπου 9 χρόνια πριν
$3000-5000 USD
Πληρωμή κατά την παράδοση
The attached list of equipment were purchased and installed in the client Food Laboratory located in Kabul, Afghanistan, on 05.June.2013. However, none of this equipment have been used since the installation date. The client now has a requirement to
1. Re-calibrate this equipment to bring it to manufacturer’s specifications
2. Provide hands-on technical training for the laboratory staff on using this equipment. We require a training period of 10 work days after calibration is completed. This training period should be divided as follows:
a. Gas Chromatograph (Item 9): 3 days
b. HPLC System (Item 10): 3 days
c. HPLC/MS (Item 11): 2 days
d. Other Equipment (Items 1-8): 2 days